Thursday, May 21, 2026

Do Pole Attachment Issues Threaten BEAD Projects?

On May 12 researchers Alex Karras and Michael Santorelli of the Advanced Communications Law & Policy Institute at New York Law School published a report and analysis of the cost of getting access to utility-owned poles as part of the deployment costs under the historic Broadband Equity, Access, and Deployment (BEAD) Program. The bottom line is that projects funded by BEAD are expected to lay 188,287 miles of aerial fiber on 3.9 million poles within 2,053 separate electric utility service territories. Using rough estimates, the estimated pole costs that BEAD contractors will have to pay in order to attach to poles range from $534 million to $4.63 billion nationwide.

Every BEAD deployment contractor had to estimate actual pole attachment costs as part of the application process. The study’s authors were not trying to duplicate these estimates. However, the range of estimates could be a sign that actual costs will vary widely. In a situation where contractors are facing tight deadlines and where actual costs are uncertain, pole attachment issues could become the focus of a lot of deployment problems. Coming on top of a renewed legal battle between Comcast and Appalachian Power Company, the large range of attachment prices shows that there is tremendous room for disagreement between broadband contractors and pole owners.

 

According to the report, pole ownership and regulation follow a “scattershot” approach. Electric cooperatives play a disproportionate role. Although they only serve 13% of electric customers, about 40% of BEAD aerial fiber will be deployed across their territories. The FCC has jurisdiction over poles owned by investor-owned electric utilities (IOUs) in 27 states. In the other 23 states, IOU poles are regulated by state public utility commissions. Regulation of poles owned by cooperatives and municipal electric utilities differs among states. The authors speculate that: “[i]n states where cooperatives and municipal electric utilities are unregulated, there are few guardrails in place to provide predictability and consistency in how pole-related costs are set, increasing the chances that BEAD subgrantees could encounter higher-than-expected pole fees from these entities.”

Electric utility pole issues have a significant effect on broadband deployment. The National Telecommunications and Information Administration (NTIA) has tried to address regulatory problems by extending the reach of the FCC’s rules. The FCC recently showed its willingness to act quickly in resolving pole disputes by expediting its decision in a dispute between Comcast and Appalachian Power Company. Comcast alleged that Appalachian Power was charging it for pole damage that was caused by third parties. The Commission ruled that Appalachian Power could only charge Comcast for the incremental cost of its project.

However, Comcast recently approached the Commission complaining that Appalachian Power was refusing to abide by its ruling. Thus, it remains to be seen whether tougher action by the FCC or NTIA will translate into a quicker, less contentious process that lowers cost or whether it leads to a rise in litigation that slows everything down.

Using a variety of independent studies, the researchers chose low, medium, and high estimates of pole costs depending on whether a pole just needs equipment added or whether it needs replacement. Their estimates are limited to electric utility-owned poles, which constitute about 70% of the total. Including all poles would raise the price significantly. The estimates for the cost per touched pole were $75 (low), $175 (base), and $450 (high). The estimates for the percentage of poles that will have to be replaced were 3% (low), 4% (base), and 8% (high). Finally, the estimates for the cost of replacing a pole were $2,000 (low), $3,500 (base), and $9,000 (high). Using the base assumptions produced an estimate of $1.25 billion or roughly 6 percent of BEAD deployment funds. The boundary estimates were $534 million (low) and $463 billion (high). This leaves a lot of room for disagreement between BEAD contractors and pole owners.

What can be done? The NTIA requires cooperatives and municipal utilities that participate in the BEAD program as subgrantees to comply with FCC pole attachment rules as a condition of accepting BEAD funding. The rules cap rates and charges that pole owners can impose on contractors. They also create timelines for processing applications and require regular progress reports. The authors also advocate letting states use some of the remaining $21 billion in nondeployment BEAD money to offset unexpected pole attachment costs. They point to successful models in Texas and North Carolina as good examples. State regulators could also rationalize pole issues as well as the accompanying permitting, rights of way, and easement issues that accompany them.

With proper policies in place, broadband providers around the country will soon be engaged in a major deployment effort to significantly expand coverage to unserved and underserved areas. In a project of this scope, problems are inevitable. But many of these problems, including pole attachments, can be managed better if regulators and broadband providers perform proper due diligence, build strong relationships, and create transparent, predicable processes.